Critical infrastructure replacement at Kangaroo Island Middle River Water Treatment Plant

In January 2020, the Middle River Water Treatment Plant (WTP) – which supplies drinking water to more than 1500 households and businesses on Kangaroo Island – was significantly damaged by bushfires.

Damage was caused to the plant’s electrical equipment, remote monitoring and network controls, communications systems and several buildings on site, rendering it temporarily inoperable.

Changing the configuration of the local water network, carting water onto and around the Island, and the assistance of a temporary mobile filtration plant supplied by the Australian Army meant a continued and safe water supply for SA Water customers was sustained to the Island during the fire. In parallel to this, a number of people including electricians, fabricators, construction workers, coordinators, engineers, and water treatment and quality experts worked together to clear debris and re-establish the site, getting the treatment plant back up and running in under two weeks.

While the WTP had resumed normal operation, two new challenges caused by the initial fire damage were discovered and Water Engineering Technologies stepped in to help.

Challenge #1

In late 2020, Middle River Treatment Process Officer Michael Webber and Water Treatment Operator Troy Kirby discovered corrosive caustic soda seeping from small cracks in two caustic tanks, caused by radiant heat from the fires.

The leaks didn’t result in any impacts to water quality or safety, but as the tanks are an important part of maintaining optimal PH levels for water treatment at the plant, their ongoing structural integrity needed to be addressed. Michael and Troy recommended urgent replacement of the tanks, prior to the next peak summer period, to eliminate the potential risk of plastic welds or the tanks themselves cracking and failing.

Solution #1

A condition assessment and investigation by Project Technical Officer Wade Collyer in December 2020 confirmed this approach and W.E.T carried out site inspections to determine the works required to implement a permanent solution.

Following a two-month lead time from order of the tanks, the team installed two double walled, self-bunded 3.3 kilolitre chemical tanks on a concrete stand. The scope of works, included:

  • disconnection of existing pipework and electrical control system and sensors
  • removal of old tanks and steel stand
  • civil works
  • installation of new tanks
  • reconnection of the inlet and outlet pipework
  • recalibration, installation and integration of level sensors and instrumentation.

Guided by Project Coordinator Tyson Swanbury, the project was delivered by team members from Water Engineering Technologies’ Berri, Murray Bridge and South Para engineering workshops.

Mechanical Apprentice Sam Butterworth was responsible for the design and pour of the tanks. Sam also designed, developed and installed all new pipework.

Electrical Tradesperson Tristyn Laccos-Barrett integrated the caustic tank level transducers and the dual leak alarm system with the current control system.

Challenge #2

The plants current turbidity analysers weren’t running as effectively as they were prior to the fire damage, due to elemental exposure and accessibility issues.

The analysers are a critical control point used to prevent the entry of waterborne pathogens into drinking water. The replacement of three turbidity analysers and the construction and installation of an open enclosure to shelter the assets to prevent them from overheating in hot weather was important to the ongoing operation of the plant.

As an added challenge, documentation and site drawings had been destroyed in the fire. The WTP’s electrical cabling system therefore required testing and verification onsite during construction, to enable the W.E.T team to work safely, efficiently and complete the work in a short timeframe, so the plant could continue to meet customer demand.

Solution #2

W.E.T team members installed new turbidity analysers, enabling better data capture, safer access to the turbidity analysers and instrumentation, and a more user-friendly system, giving a true representative turbidity sample from the filters used at the Middle River WTP.

Senior Tradesperson Peter McGowan designed the new panel and configured the turbidity analysers.

Rusted outlet on caustic tankWater treatment system

Above left: rusted outlet on leaking caustic tank
Above right: the new caustic tanks on concrete stand

Water Engineering Technologies staff

Our project team of (L to R) Paul Rands, Gary Symonds, Ben Childs, Sam Ingerson,
Sam Butterworth and Troy Kirby.